Paint Systems Case Study

Ford Motor Company Hermosillo, MX Paint Systems Case Study

Project Details:
W.J. O’Neil provided necessary material, fabrication, and field installation for the paint department for the Ford Assembly Plant in Mexico. The project involved extensive reworking of the existing paint circulating systems. Fabrication was done in our Michigan fab shop. Our WJO Mexican operation ensured that this project stayed on budget and was delivered on time.
Customer:
Ford Motor Company, Mexico
Project Cost:
$4,500,000
WJO Role:
Mechanical Contractor